BHEL Bags Rs 3,500 Crore Order from Adani Power

Open Demat A/C

Key Announcement

BHEL announced a significant order from Adani Power Ltd to set up a 2×800 MW thermal power plant in Raipur, Chhattisgarh.

Open Demat A/C

Contract Details

The contract, worth over Rs 3,500 crore, includes supplying equipment and overseeing erection and commissioning of the power project.

Open Demat A/C

Supercritical Technology

The power project will use advanced Supercritical Technology. Equipment like boilers and turbines will be manufactured in BHEL’s Trichy and Haridwar plants.

Open Demat A/C

Timeline

Unit-1 of the project will be supplied within 35 months, and Unit-2 will follow within 41 months, as per the agreement.

Open Demat A/C
Open Demat A/C
G-L92HWH8MZR