L&T Powers Ahead with Mega Mumbai Metro Line 4 Deal
Order Value & Classification The contract is classified as “significant” by L&T, with an estimated value ranging between ₹1,000 crore and ₹2,500 crore
Project Details Package CA-298 covers electrification of the 24.72 km Mumbai Metro Line 4 from Bhakti Park to Cadbury Junction, including 22 elevated stations
Scope of Work Work includes power supply, traction systems, SCADA integration, electrical and mechanical installations, lifts, escalators, testing, commissioning, and five years of maintenance
Strategic Importance This is L&T’s third consecutive win on the Line 4 & 4A corridor, following earlier orders for rolling stock, signalling systems, and ballast-less track works
Company & Market Update L&T reported strong Q2 FY26 results with higher profits and revenues. Shares traded marginally higher at around ₹4,062 on the BSE